Jump to content

Absolutely NON FISHING


irishfield

Recommended Posts

Not exactly what I had planned for this weekend of beautiful weather, but what can you do other than enjoy the moments that come with it...and be thankful for what you have around you, exhausted or not! :sleeping_02:

 

Yesterday we pulled a 1000 foot length of 25KVA primary from the closest concession rd with a power line to the cement transformer vault on my son's new house build and backfilled the trench a foot or more with sand. Previously we had buried two sections of BIG O about 100 feet long each at the road end (as town wouldn't allow an open trench to be left on the road allowance) and two lengths about 250 feet long from the laneway crossing over to the house, with one going in/out of the transformer vault (as the contractors/cement trucks and such needed to get in the yard and safety regs needed the footings backfilled before framing started).

 

Primary in and sand on top

 

dtrench.jpg

 

This morning started out with us spooling off 2 x 350 foot lengths of Direct Bural 14-2 low voltage wire I have on a 7000' spool in the hangar. Then we thought we'd get creative to respool it onto a smaller spool. Redneck's are us...

 

redneckwinder.jpg

 

<iframe width="420" height="315" src="http://www.youtube.com/embed/Z3xTy2e3QpA" frameborder="0" allowfullscreen></iframe>

 

Today we put down over 7000 feet of "misc" wire. 3 x 1000 foot runs of phone line, 2 x 1000 foot runs of RG-11 cable all the way to the concession road. 3 x 4pair-24awg, 2 x 14-2, 2 x RG6 cable about 350 feet long to the laneway with 100 feet extra for security cameras and power for same or laneway lights. All of these needing to be pulled thru that 250 feet of Big O from laneway to house. So in all 12 cables/wires thru the duct. That one took Son and youngest daughter pulling while I feed all of the wires smoothly thru from the trench end.

 

Leah showed up with lunch for everyone (after getting the turkey in the oven), just in time to be put to work pulling 180 feet of secondary 3 x 4/0 from the vault to the house. That took Leah, daughter and I all pulling with everything we had to the point of exhaustion, while son fed the spool in at the vault.

 

With that all done, then they stuck me on the bulldozer with what was left of daylight, backfilling the trench. Figure that I have about 6 hours more to get it done tomorrow. Like I said, nowhere near what I had planned for myself this weekend... but selfishness aside, it was a great family day today with a lot of laughs.

 

Jennifer happily back in her Toronto apartment, thankful to be back there and trying to get back to as normal a life as she can. Me happy I have our son one step closer to getting his house done (and out of mine :whistling: ). Youngest daughter enjoying her day in between working on a major architecture project that's due on Tuesday am. And thankful for Leah that ties us all together and makes life just that much more enjoyable.

 

Now be careful whom you give the white hat to and don't leave the keys in the tractor. :sarcasm:

 

konkubota.jpg

 

<iframe width="420" height="315" src="http://www.youtube.com/embed/h7gKqK7aNR8" frameborder="0" allowfullscreen></iframe>

 

Hopefully he'll be in by winter and learn what a heating bill is first hand!! :w00t::D

 

dhouse.jpg

Edited by Roy
Link to comment
Share on other sites

Well today wasn't quite as fun, although we did add a generation to the Thanksgiving "festivities" with Leah's father lending a hand. My plan was to be up early and get the trench filled with enough time to get in a quick flight and then get the boat/gear ready for Leah and I to head North in the am to close up camp. Well that all went out the window about 11:15 as I slide into the soup in the low area of the trench that was water filled.

 

dozer1.jpg

 

Amazed my little 350 kept running on this angle.. but I couldn't get anywhere with the left track bound into the side of the trench. Luckily the $8000 length of 25KVA primary cable was on the right side of the trench so the track never got to it. I did bugger the 3 runs of phone and 2 runs of cable coax though, as the track gaps caught it.

 

The following operation only took us about 3 hours :wallbash: Just wish we had of thought to grab the contractors yard lift first before trying anything else or there wouldn't be the need for 40 cable splices to be made as we had to dig up behind the machine and find good line.. cut.. cut ahead and add pieces in. 36 phone wires and 4 cable coax splices (all pulled above ground in Big O so the splices aren't buries). BTW a Kubota key fits a John Deer yard lift for anyone finding them self in a similar situation.. :whistling:

 

dozer2.jpg

 

dozer3.jpg

 

dozer4.jpg

 

dozer5.jpg

 

dozer6.jpg

 

dozer7.jpg

 

dozer8.jpg

 

Not the nicest thing to do to my skidder winch...but what can ya do! That little dozer weights 6800 lbs! Shortly after this shot... one of those sling cables broke, but the other held enough to toss some logs under the track. And then we lifted again, and more logs.

 

dozer9.jpg

 

And then we pulled and nobody told #1 son my dozer stalled and he kept going and broke that 5/8 cable ! :w00t: Notice I'm ready for something of that sort and my head is DOWN!

 

dozera.jpg

 

Uni - Uni or Square ??

 

dozerb.jpg

 

3 generations knot tying ! Only one smart guy with gloves... At 70 Leah's father doesn't really seem to care..

 

dozerc.jpg

 

This time we're out.

 

dozerd.jpg

 

Then got the pleasure of a 1/2 hour of digging the mud out of the track mechanism with a crow bar and 4 hours of riding the thing to finish. Guess we'll be a day later getting North, but the son has no more excuses left that Hydro can't hook him up yet! :D

Edited by irishfield
Link to comment
Share on other sites

Just think of the glorious memories, Wayne. Remember, some folks buy a ready built house, and the only memories they have is of moving day and the 3 dozen people who showed up to help them dust off the counters and cupboards. You guys did good.

Link to comment
Share on other sites

Thats quite the way to spend the holdiay dry.gif . But in a year or so I bet you'll celebrate Thanksgiving in your son's house and all have a good laugh about the day Wayne got the dozer stuck in the trench! You raised a great family there Wayne & Leah - congrats.

Edited by spincast
Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
  • Recent Topics

    Popular Topics

    Upcoming Events

    No upcoming events found

×
×
  • Create New...